Residential · 22 floors · Whitefield, Bengaluru
Riverside Tower — Block B
Overall progress
64%
Budget spent
₹38.2 Cr
of ₹52 Cr · 73%
Schedule
4 days late
Handover target · Aug 2027
Open issues
17
3 high priority
Milestones
Full scheduleFoundation
Done
Structure L1–L12
Done
Structure L13–L22
−4 days
MEP rough-in
On track
FacadeMar 2027
Finishes and handoverAug 2027
Budget
Materials₹19.4 / 24 Cr
Labour₹11.6 / 16 Cr
Equipment₹4.9 / 7 Cr
Contingency₹2.3 / 5 Cr
Latest issues from site
All issues| # | Issue | Location | Owner | Priority |
|---|---|---|---|---|
| 214 | Hairline crack in column C-4 | Level 6 | S. Rao | HIGH |
| 213 | Guardrail missing at stair core | Level 9 | Safety team | HIGH |
| 211 | Conduit clash with duct, corridor B | Level 5 | MEP contractor | MEDIUM |